Most statements of work get read carefully twice. Once by the customer before they sign, and once by your delivery team after something goes wrong.

The second reading is the expensive one. It usually happens in month three, when the customer says a report was included and your project manager goes looking for proof. Whatever the SOW says at that point is what you're working with. So it pays to read it properly while you can still change it.

This checklist is written for the people who will deliver the work. Use it on any significant SOW before the signature date is set.

Before you start: gather everything that makes a promise

The SOW rarely stands alone. Pull together the proposal, any questionnaire or RFP answers, the pricing build-up, the delivery estimate and the emails where scope was discussed. If the contract says the proposal forms part of the agreement, it matters as much as the SOW.

Then read the SOW with one question in mind: if we were held to every word of this, could we deliver it at this price?

1. Deliverables

  • Is each deliverable described well enough that two reasonable people would agree whether it's done?
  • Are quantities stated? "Reports" and "training" mean little without a number. Five reports or twenty? One session or one per site?
  • Is there anything in the proposal or the demo the customer might believe is included but isn't listed?
  • Are any deliverables described as "standard", "typical" or "as required"? Each of those words needs a definition or a limit.

2. Assumptions

Assumptions are where a lot of the risk sits. Your estimate depends on them, so they need to be in the SOW, not only in your spreadsheet.

  • Does the SOW state what you assumed about data volume, data quality and the number of source systems?
  • Is the number of integrations fixed, and is each one named?
  • Does it state which environments the customer will provide and when?
  • Is there an assumption about how quickly the customer will review and approve work?

If an assumption your price depends on isn't written down, the customer hasn't agreed to it. We cover this in more depth in SOW assumptions and exclusions.

3. Customer responsibilities

  • What does the customer have to provide: people, data, access, decisions, sign-offs?
  • Is there a date or turnaround attached to each one?
  • What happens to your timeline and cost if they're late? Is that written down, or will it be a negotiation?

4. Exclusions

  • Is there an explicit list of what is not included?
  • Does it cover the things customers most often assume are included: extra reports, data cleansing, additional training, post-launch support, third-party licences?
  • Is it specific enough to point to in a disagreement without sounding like you're hiding behind fine print?

5. Acceptance

  • How does a deliverable get accepted? Who signs off, and within how many days?
  • Are the acceptance criteria objective, or could the customer hold sign-off open indefinitely?
  • How many rounds of testing are included, and what counts as a defect versus a new request?

6. Change control

  • Is there a written process for changes, with an owner on each side?
  • How will changes be priced: at your standard rates, by quote, from a pool of hours?
  • Does the process kick in before work starts, or is there a risk your team does the work and argues about payment later?

Our piece on scope creep in fixed-price projects goes into why this section matters more than it looks.

7. Timeline and milestones

  • Does the timeline include the customer's review and approval time at the pace they actually work?
  • Are payment milestones tied to things your team controls, or to customer approvals that could drift?
  • Is there any date in the SOW your delivery lead hasn't seen?

8. Staffing

  • If named people appear in the SOW or proposal, are they actually available for the whole project?
  • Does the plan assume a full team from day one, or does it allow for ramp-up?
  • Are subcontractor rates and availability confirmed on terms that match what you're promising?

Clauses to send to your legal team

Some of what you'll notice while reviewing a SOW belongs with your lawyers, not your delivery team. Liquidated damages or service credits tied to dates, deemed acceptance, warranty periods, key personnel terms and the order of precedence between the contract, the SOW and the proposal are common examples. Note what each one means for delivery and margin, and send it to legal. They decide what to change.

The test at the end

When you've worked through the list, ask your delivery lead one question: could you explain every line of this SOW to the customer today, without asking sales what it means?

If the answer is yes, you're in good shape. If it's "mostly", the gaps are worth finding now. They'll be found either way.

Akili Etefia is the founder and principal of Kenley Pursuit. Akili spent about five years in proposal and bid management on more than 100 public-sector proposals, including proposal pricing and evaluation, after beginning their career in audit training. More about Kenley Pursuit

Questions

Who should review a SOW before it is signed?

At minimum, the person who will lead delivery, someone who understands the product or technical solution, and whoever owns the commercial terms. Contract clauses should also go to your legal team. The salesperson should be in the conversation but should not be the only reviewer.

How long should a SOW review take?

For a significant deal, plan for a few days, not a few hours, and schedule it before the signature date is fixed. The review is only useful while the SOW can still change.

Is a SOW review the same as a contract review?

No. A SOW review looks at what you are committing to deliver and whether the price and plan support it. Contract terms such as liability, indemnities and warranties are for your legal team.