Ask a finance lead why a project lost money and you'll usually hear about the estimate. The build took longer than planned. The rates were too thin. The discount was too generous. Sometimes that's the whole story.
More often, when you trace the overrun line by line, the estimate for the work everyone knew about was close enough. The money went on work nobody put in the estimate at all.
A sales engineer told the customer the reporting module "can handle that." A delivery lead agreed, in a workshop two weeks before signature, to run training in two cities instead of one. The SOW says "migration of existing records" without saying how many, from which systems, or in what condition. Every one of these is a promise. None of them has a line in the cost model.
We call that gap an unpriced commitment. It's a common reason a contract that looked healthy at signature becomes a project that quietly eats its own margin.
Why the estimate looks fine and the project doesn't
Estimates are built from a scope document. Promises aren't kept in one.
They're spread across the proposal, the answers to the customer's questions, the demo the customer's team remembers, the email thread about single sign-on, and whatever was said on the final call when the customer pushed back on the timeline. The person building the estimate usually works from the SOW and a scoping call. They don't see most of the rest.
So the cost model and the customer's expectations start drifting apart before the contract is even signed. Nobody did anything wrong. The two documents were simply never put side by side.
Where unpriced commitments tend to hide
They show up in the same places on most implementation projects:
- Capability answers. "Yes, we support that" in a questionnaire, when the honest answer was "yes, with configuration work."
- The demo. Customers buy what they saw. If the demo used a custom dashboard or sample data, they may expect both.
- Integrations called standard. "Standard API integration" can mean an afternoon or three weeks, depending on the other system.
- Data migration. Volume, sources and data quality are often assumed rather than checked.
- Customer-specific reports. Each one feels small. Twelve of them are a workstream.
- Training, documentation and support after go-live. Easy to agree to, rarely costed in detail.
- "We'll work that out in discovery." A phrase that moves the decision past signature, when it's much harder to price it.
Why nobody catches them
Each commitment looks too small to escalate on its own. And each one sits between teams.
Sales owns the relationship and the close. Delivery owns the plan. Finance owns the model. A promise made in a sales conversation and missing from the delivery plan belongs to all three, which in practice means it belongs to nobody until it turns up as unbilled hours in month four.
There's also a timing problem. The people best placed to spot an unpriced commitment, the ones who will actually do the work, usually see the deal after it's signed. By then the only question left is who absorbs the cost.
How to find them before you sign
You don't need new software for a first pass. You need a few hours, the right documents and the right people in the room.
Start with one list. Pull every commitment out of the SOW, the proposal, the questionnaire answers and the key emails into a single table. One row per promise, with a note of where it came from. If someone remembers saying something on a call, it goes in too.
Ask three questions of each row. Who will deliver this? Roughly how much effort is it? Where is it in the price? A row with a blank in the last column is an unpriced commitment.
Decide what happens to each one. Some get priced in. Some get scoped out, in writing, as an exclusion or an assumption in the SOW. Some become a paid change request you can raise later. A few you'll accept on purpose, because the deal is worth it. That's a fine outcome too, as long as it's a decision someone made with the number in front of them.
Write it down where delivery will see it. The list, and what was decided about each line, should go to the delivery team with the contract. Otherwise the same commitments get rediscovered, one argument at a time, during the project.
Any contract clauses that come up along the way, such as acceptance terms or service credits, go to your legal team with a note on what they mean for delivery. Your lawyers decide what to change.
What changes when you do this routinely
The first time a team runs this exercise on a live deal, the list is usually longer than anyone expected. That's normal, and it's useful. It shows where your sales process creates commitments that your pricing process never sees.
Over a few deals, the same sources keep coming up. Maybe it's questionnaire answers, maybe it's demos, maybe it's one integration everyone keeps calling standard. Fix those at the source and the list gets shorter.
Here's a quick test you can run this week. Take the last fixed-price project that went over. Find the first piece of work that wasn't in the original estimate, then look for where it was promised. In a lot of cases you'll find it in an email or a proposal answer dated before the signature.
Related reading: why "free" customizations aren't free, and how to review a statement of work before you sign it.
Questions
What is an unpriced commitment?
Anything your company has promised a customer that has no matching line in the cost model or delivery plan. It can sit in a SOW, a proposal answer, a demo, an email or a conversation before signature.
Isn't this just scope creep?
Scope creep is new work the customer asks for after signature. An unpriced commitment was already agreed before signature, often without anyone noticing. The customer can fairly say it was always included, which makes it much harder to charge for.
Who should own the list of commitments?
One named person, usually on the delivery or commercial side, who did not build the estimate and is not paid to close the deal. What matters most is that one list exists and someone is accountable for reconciling it with the price.