The contract is signed and the project is underway. A few weeks in, the customer asks for one more report. Then a small change to a workflow. Then training for a team that wasn't in the original plan. Each request sounds reasonable and each one is small. Your team says yes, partly to keep a new customer happy and partly because nobody is quite sure whether the work was already included.

Six months later the project is behind and over budget, and nobody can point to the moment it went wrong. It went wrong in small pieces, every time a new request was handled as if it had already been paid for.

Our piece on scope creep in fixed-price projects looks at how much of this gets built into the SOW before signature. This one is about what happens after: how to tell, quickly and calmly, whether a request is new work.

Why do teams do extra work for free?

Mostly because they can't tell whether it's extra. That tends to happen when:

  • Scope lives in several places. The SOW, the proposal, the questionnaire answers and a few important emails all describe the work, and they don't always agree.
  • The people who sold the deal have moved on. The account executive is working the next deal and the solution engineer is in another customer's workshop.
  • The SOW describes outcomes without limits. "Train customer administrators" with no number of sessions is hard to hold a line on.
  • Nobody owns the question. Project managers are judged on keeping the customer happy, so yes feels like the safe answer.

Nobody is acting in bad faith here. What's missing is a shared, written answer to "what is included?"

What a scope baseline is

A scope baseline is a plain-language record of what you agreed to deliver, built from the signed contract, the SOW and anything they pull in. It sets out:

  • every commitment, with its source
  • deadlines and milestones
  • quantities and limits: sessions, environments, users, integrations, reports
  • who owns each commitment on your side
  • which part of the price pays for it
  • what is explicitly out of scope

It sits beside the contract as the working version your delivery team checks every day. Where the two differ, the contract wins.

How to build one

A workable baseline takes a few days, and the best time to build it is before signature, while the scope can still be tightened.

Gather everything that makes a promise. The contract, the SOW, the proposal if the contract incorporates it, and the key emails and questionnaire answers. If the contract has an order-of-precedence clause, your legal team can tell you which document wins when two disagree.

List every commitment. One row per commitment, with the exact wording and where it came from. Pay attention to quantities. "Up to four training sessions" is a limit. "Training as required" is an open door.

Add owners and price lines. For each row, name the team that delivers it and the part of the price that pays for it. Rows with nothing paying for them deserve a second look.

Write down what's out of scope. List the things a customer might reasonably expect that you didn't agree to: extra environments, more users, new integrations, data cleansing, support beyond the hypercare period. If the SOW is silent on something, note that too.

Walk the delivery lead and the account lead through it. Both should be able to answer "is this included?" by checking the baseline, without calling each other.

Handling a request once you have it

Use the same short routine every time:

  1. Log the request. Who asked, when, and exactly what they want.
  2. Check it against the baseline. Included, partly included, or not included.
  3. If it's included, do it. Deliver what you promised, on time.
  4. If it isn't, say so early and kindly. Point to the baseline, describe what the work involves, and give a price and a timeline.
  5. Follow the change process in the SOW. Get written approval before the work starts. Work done before approval is much harder to bill.
  6. Keep a record. Requests, decisions and approvals in one place. It helps at renewal time too.

Tone matters a lot here. "That's a good idea, and it's outside what we scoped. Here's what it would take" lands very differently from a flat no.

An illustrative example

A made-up example to show the pattern, not a client result.

A software company is implementing its platform for a regional distributor. The SOW includes "monthly operational reporting to the customer's project sponsor." Four months in, the customer asks for a weekly version of the same report for each of their three warehouses.

Without a baseline, the project manager adds the reports, because reporting is "already in the contract." That's three new weekly reports, built and run for the rest of the project. With a baseline that records "one monthly report, to the sponsor", it's clear the request is a change. The team prices it, the customer approves it through the SOW's change process, and the work is paid for. The relationship is fine, because the customer can see exactly where the line was.

Where it really starts

The cleanest change process starts before signature. If the SOW says "included" against an open-ended requirement, you've already given away the limit you'll need later. Specific quantities, written assumptions and an honest exclusions list are what make a change request feel fair to the customer instead of opportunistic.

Related reading: SOW assumptions and exclusions, and the sales-to-delivery handoff.

Akili Etefia is the founder and principal of Kenley Pursuit. Akili spent about five years in proposal and bid management on more than 100 public-sector proposals, including proposal pricing and evaluation, after beginning their career in audit training. More about Kenley Pursuit

Questions

What is a change request?

A request from the customer for work that differs from what the contract and SOW describe: something new, something more, or something done differently. Most SOWs set out how changes are requested, priced and approved.

Will charging for changes hurt the customer relationship?

It usually goes better when the scope was clear from the start. What strains a relationship is a surprise invoice months later, or a team that quietly falls behind because it took on unpaid work.

Should small requests be absorbed as goodwill?

Sometimes, as long as it is a decision and someone tracks the total. Many small yeses can add up to a large unpaid piece of work.