Most technology and services firms have a handoff. Sales closes the deal, books a kickoff, shares the CRM notes and the signed SOW, and delivery takes it from there.
The trouble is timing. By the time delivery reads the deal properly, the price is fixed, the dates are in the contract and the customer has been told what they're getting. A handoff after signature can only report problems. A handoff before signature can still fix them.
Why the usual handoff breaks on fixed-price work
The knowledge delivery needs is created during the sale. It lives in the account executive's memory, the solution engineer's notes, a dozen email threads, the answers to the customer's questions and the demo the customer remembers best.
The SOW captures the price and a list of deliverables. It rarely captures the reasoning behind them: what was assumed about the customer's data, who would make decisions, how many rounds of testing were priced, which integration was "probably standard."
So delivery inherits the commitments without the assumptions. On time-and-materials work, that gap becomes a difficult conversation. On fixed-price work, it becomes unbilled hours.
There's a quieter problem too. Sales and delivery are measured on different things, and both are behaving sensibly. When the only review happens two days before quarter end, a delivery lead who raises a concern gets cast as the person slowing revenue. A handoff that's scheduled and routine takes the politics out of it.
Move it before the signature
The change is easy to describe: the person who will run the project reads the deal before the customer signs it, with enough time left to change what's wrong.
That needs three things.
A fixed point in the sales process. After the effort estimate and draft SOW exist, before the contract goes out for signature. If the customer ran a formal RFP, before the final proposal is approved, because the proposal is often part of the contract.
A named delivery reader. Ideally the person who'll lead the project. Someone who didn't build the estimate.
A written result. Go, go with conditions, or stop. Conditions are specific: "add the data quality assumption to the SOW," "confirm the integration lead is free from the start date."
The pre-signature handoff checklist
Not every line applies to every deal. What matters is that someone has looked.
What was actually sold
- Can the delivery lead explain every line of the SOW to the customer today, without asking sales what it means?
- Does every deliverable in the proposal or demo appear in the SOW, or is it clearly out of scope?
- Were features shown in a demo, or described as "on the roadmap," that the customer may believe are included?
- Were promises made in emails, questionnaire answers or calls? Are they collected in one place?
Assumptions and customer dependencies
- Are the assumptions in the SOW itself, not only in the estimate spreadsheet?
- Is it clear what the customer must provide and by when: data, environments, access, people, decisions?
- Is data migration scoped by something you can check, or by a hope that the data is clean?
- Is each integration named and described well enough to estimate?
- Is there a written answer for what happens when the customer is late?
The estimate
- Did anyone who will deliver the work see the estimate before it was priced?
- Is contingency named and sized, or spread through line items where it'll be spent early?
- Is testing bounded: how many rounds, and what counts as passing?
- Does the timeline allow for the customer's review time at the pace they actually work?
Staffing
- Are the people or roles in the estimate actually available on the start date?
- If the proposal names key people, can you keep them on the project for its whole length?
- Are subcontractor rates and availability confirmed on terms that match what you're promising?
Commercial terms
- Are payment milestones tied to things your team controls?
- Is there a change process, with a named owner on each side and a way to price changes?
- Is the exclusions list specific enough to point to in a disagreement?
Clauses to send to your legal team
The handoff shouldn't turn delivery leads into contract lawyers. The job is to notice the clauses that affect delivery and margin, and send them to the people qualified to decide. Service credits or damages tied to dates that depend on the customer, deemed acceptance, key personnel terms, warranty periods and the order of precedence between the contract, the SOW and the proposal are typical. Flag each one with a short note on what it means for delivery. Legal decides what changes.
What the handoff produces
One short record, written before signature and handed to delivery with the contract:
- what was sold, in plain language
- the assumptions the price depends on, and where each one sits in the SOW
- what the customer has agreed to provide, with dates
- open risks, each with an owner
- clauses sent to legal, and their answer
- the result: go, go with conditions, or stop
That record replaces the kickoff scramble. Delivery starts the project already knowing what was promised and why.
Who should own it
Whoever owns the handoff should be paid neither to close the deal nor to stop it. In many firms that role falls to a delivery or professional services lead who is already stretched, and the step gets skipped on exactly the deals where it matters most: the big, late, fixed-price ones.
Two things help. Keep it short and predictable, so sales can plan around it. And on the deals that carry real risk, bring in someone outside the deal team who has no stake in who was right.
Related reading: why sales and delivery remember different deals, and how to review a statement of work.
Questions
Won't a handoff before signature slow the deal down?
It adds a step, so plan for it. Scheduled early, it usually runs alongside legal and pricing. The deals that slow down most are the ones where scope questions surface during contract negotiation instead.
Isn't this what the kickoff meeting is for?
A kickoff can share what was agreed. It can't change it. The checklist here is only useful while the SOW is still a draft.
Who should run the handoff?
Someone who is paid neither to close the deal nor to stop it. On significant deals, that is often a senior delivery lead or an independent reviewer who sits outside the deal team.